Aberdeen beach, Links Road to Esplanade
Beach park and pedestrian connections
The beachfront programme combines play and event spaces with improved walking and cycling connections.
Pedestrian route approved; wider works reported underway · evidence dated 2025-08-06
Responsible body: Aberdeen City Council
Latest evidence: The council records approval of the pedestrian spine and says Broad Hill improvements had completed in July 2025. This does not confirm completion of the entire beachfront programme.
Next thing to establish: What is the approved cost, including ongoing maintenance?
Progress, funding and source
- Cost
- Not established by the evidence checked.
- Funding
- Not established by the evidence checked.
- Area covered
- No official project-to-ward mapping has been verified; no ward allocation is inferred from the city name.
No verified ward footprint is assigned.
Pedestrian spine to feature in new leisure area at the beach →
Source checked 2026-10-17. A plan or announcement is not proof of completion.
Questions for the next progress report
- Which funding is committed, and what remains conditional?
- Which neighbourhoods are covered by an official project plan, and which benefits still need testing?
- What is the next published milestone, and what evidence will show residents benefit?
How to track delivery →Aberdeen City Council housing and homelessness services
Council-home safety and empty-home improvements
The housing regulator is monitoring electrical safety work, long waits to re-let empty homes and pressure on homelessness services. Its April 2026 plan requires further improvement.
Regulatory monitoring and improvement requirements; resolution not verified · evidence dated 2026-04-02
Responsible body: Aberdeen City Council, monitored by the Scottish Housing Regulator
Latest evidence: The regulator asks for monthly updates on electrical inspection work and quarterly engagement on homelessness. It also requires better performance on re-letting and rent arrears. These are reported concerns, not findings that every home is unsafe.
Next thing to establish: What is the approved cost, including ongoing maintenance?
Progress, funding and source
- Cost
- Not established by the evidence checked.
- Funding
- Not established by the evidence checked.
- Area covered
- No verified current ward footprint is assigned. The named site or council-wide remit is not proof of benefits to every ward.
No verified ward footprint is assigned.
Aberdeen City Council: housing engagement plan, April 2026 to March 2027 →
Source checked 2026-10-17. A plan or announcement is not proof of completion.
Questions for the next progress report
- Which funding is committed, and what remains conditional?
- Which neighbourhoods are covered by an official project plan, and which benefits still need testing?
- What is the next published milestone, and what evidence will show residents benefit?
Make council homes safe and bring empty homes back into use →