Named local schemes and plans, with the responsible body and the latest stage established by the source checked. A proposal, funding announcement and completed project are different things.
Union Street, The Green and Market Street
New city-centre market
A new market venue is designed to bring food businesses and improve walking connections between Union Street and the stations.
Construction reported progressing; completion not verified · evidence dated 2025-08-06
Responsible body: Aberdeen City Council
Latest evidence: The August 2025 council update says market construction is progressing alongside city-centre street improvements. This is evidence of work in progress, not a public opening.
Next thing to establish: What is the approved cost, including ongoing maintenance?
Progress, funding and source
- Cost
- Not established by the evidence checked.
- Funding
- Not established by the evidence checked.
- Area covered
- No official project-to-ward mapping has been verified; no ward allocation is inferred from the city name.
No verified ward footprint is assigned.
Pedestrian spine to feature in new leisure area at the beach →
Source checked 2026-10-17. A plan or announcement is not proof of completion.
Questions for the next progress report
- Which funding is committed, and what remains conditional?
- Which neighbourhoods are covered by an official project plan, and which benefits still need testing?
- What is the next published milestone, and what evidence will show residents benefit?
Make the new market a clear route between the centre and stations →
Connect local skills to local opportunities →
How to track delivery →Aberdeen beach, Links Road to Esplanade
Beach park and pedestrian connections
The beachfront programme combines play and event spaces with improved walking and cycling connections.
Pedestrian route approved; wider works reported underway · evidence dated 2025-08-06
Responsible body: Aberdeen City Council
Latest evidence: The council records approval of the pedestrian spine and says Broad Hill improvements had completed in July 2025. This does not confirm completion of the entire beachfront programme.
Next thing to establish: What is the approved cost, including ongoing maintenance?
Progress, funding and source
- Cost
- Not established by the evidence checked.
- Funding
- Not established by the evidence checked.
- Area covered
- No official project-to-ward mapping has been verified; no ward allocation is inferred from the city name.
No verified ward footprint is assigned.
Pedestrian spine to feature in new leisure area at the beach →
Source checked 2026-10-17. A plan or announcement is not proof of completion.
Questions for the next progress report
- Which funding is committed, and what remains conditional?
- Which neighbourhoods are covered by an official project plan, and which benefits still need testing?
- What is the next published milestone, and what evidence will show residents benefit?
How to track delivery →Aberdeen City Council housing and homelessness services
Council-home safety and empty-home improvements
The housing regulator is monitoring electrical safety work, long waits to re-let empty homes and pressure on homelessness services. Its April 2026 plan requires further improvement.
Regulatory monitoring and improvement requirements; resolution not verified · evidence dated 2026-04-02
Responsible body: Aberdeen City Council, monitored by the Scottish Housing Regulator
Latest evidence: The regulator asks for monthly updates on electrical inspection work and quarterly engagement on homelessness. It also requires better performance on re-letting and rent arrears. These are reported concerns, not findings that every home is unsafe.
Next thing to establish: What is the approved cost, including ongoing maintenance?
Progress, funding and source
- Cost
- Not established by the evidence checked.
- Funding
- Not established by the evidence checked.
- Area covered
- No verified current ward footprint is assigned. The named site or council-wide remit is not proof of benefits to every ward.
No verified ward footprint is assigned.
Aberdeen City Council: housing engagement plan, April 2026 to March 2027 →
Source checked 2026-10-17. A plan or announcement is not proof of completion.
Questions for the next progress report
- Which funding is committed, and what remains conditional?
- Which neighbourhoods are covered by an official project plan, and which benefits still need testing?
- What is the next published milestone, and what evidence will show residents benefit?
Make council homes safe and bring empty homes back into use →
Make room for homes people can afford →
How to track delivery →What this local evidence covers
13 of 13 wards
Have at least one valid census comparison with the whole council. Missing measures stay visible.
Read the neighbourhood evidence →3 reviewed plans and projects
3 have a source-dated stage; 0 have some funding evidence; 0 have some cost evidence. These counts do not prove that funding or costs are complete.
Check each project →0 verified ward links
Project locations cannot be treated as a map of who benefits. Each record explains any verified ward association.
Read the sources and limits →What is still missing
The reviewed local schemes are a selected evidence collection, not a complete council capital programme.
Current service capacity, incomes, waiting lists, school demand and project outcomes need additional verified local evidence before firm claims can be made.
Project locations have not been matched to official ward boundaries. No ward-specific delivery claims are inferred.
Costs, funding and benefits are only reported where the selected official evidence states them; blank fields are not zero.
Some dated project updates have elapsed target dates. A newer completion record is needed before changing their delivery status.
The regulator’s April 2026 requirements are retained as dated concerns. Current outstanding safety-work counts and evidence that the concerns have been resolved have not been verified.